The Jakarta Light Rail Transit (LRT) system extended its route by 6.4 km on November 18, 2026, officially opening Phase 1B. This extension doubled the line’s length from the original Kelapa Gading terminus in northern Jakarta to Manggarai in the south, adding five stations and increasing the total to 11 stations along 12.2 km.
The new section connects Kelapa Gading to the Manggarai transport hub, a major interchange point for PT KAI commuter trains, local and regional buses, and the airport rail link. Three of the new stations—Matraman, Proklamasi, and Pramuka—were not fully operational at the inauguration; Pramuka has since
opened, while Matraman and Proklamasi remained closed as of mid-November 2026.
Construction and Operational Details
The extension was constructed by KSO Waskita Nindya LRS, a joint operation that includes state-owned Waskita Karya, under contract to PT Jakarta Propertindo, owned by the Jakarta government. The build cost Rp4.1 trillion (US$227 million), fully financed by the Jakarta provincial government. The entire 12.2 km line investment totals Rp12.1 trillion (US$670 million), according to Governor Pramono Anung.
Operations on the extended line continue to rely on eight two-car trainsets supplied in 2017 by Hyundai Rotem and Woojin Industrial Systems under a US$33 million contract. Each articulated set can
carry 270 passengers and reaches a top speed of 90 km/h. Post-extension, trains operate every 15 minutes from 05:30 to 20:00 along the entire route, with service limited to the original Kelapa Gading to Velodrome section until 23:00. The Jakarta Transportation Agency plans to extend full route operations to 23:00.
Ridership and Service Performance
Within the first eight days after the inauguration, the line transported more than 92,000 passengers, averaging approximately 11,500 daily with an initial promotional fare of Rp8. Data from September 2026 showed ridership exceeding 210,000 passengers for the month, marking a 58% increase compared to August 2026. The governor forecasts an
average daily ridership of about 80,000 once the line reaches full operational capacity.
PT LRT Jakarta’s President Director highlighted the increased operational responsibility following the extension, emphasizing the need to maintain safety and reliability to meet public expectations.
Future Expansion Plans
Further development is scheduled with Phase 1C, a 2 km extension from Manggarai to Dukuh Atas in central Jakarta. This phase will link the LRT to the MRT Jakarta metro, commuter rail services, and TransJakarta bus routes. Construction is projected to start by January 2027 and conclude by August 2028. The estimated cost of Phase 1C has risen from Rp2.1 trillion to
Rp2.7 trillion (US$150 million), chiefly due to procurement of approximately 16 new trainsets.
Phase 2A is planned to extend the line northward from Kelapa Gading to Jakarta International Stadium, covering 8.2 km with six stations. This phase is forecasted to begin in 2027 with a budget of Rp7.8 trillion (US$432 million), and may be funded through public-private partnerships or government loans.
Governor Pramono Anung sought support from Indonesia’s sovereign wealth fund Danantara for these expansions. President Prabowo Subianto concurred, stating Jakarta belongs to the nation and highlighting the importance of Danantara’s involvement.
Integration with Jakarta’s Transport Network
The Manggarai transport hub, the southern terminus of
the new extension, provides multiple intermodal connections. Passengers can transfer to PT KAI commuter trains that serve the wider Jakarta metropolitan area, regional bus services, and the city’s airport rail link, enhancing the LRT’s role in the capital’s urban transit network.
This interconnectivity supports the mobility needs of Jakarta’s approximately 42 million population, fostering a more integrated metropolitan transport system.