President Prabowo Subianto officially inaugurated a 6.4 km extension of the Jakarta Light Rail Transit (LRT) line on 18 November 2026. The extension, referred to as Phase 1B, more than doubled the original line’s length by expanding it from Kelapa Gading in North Jakarta to the Manggarai transport hub in South Jakarta. This addition brought the total line length to 12.2 km served by 11 stations.
Following the opening, ridership rapidly increased, with over 92,000 passengers recorded in the first eight days, averaging about 11,500 passengers daily while a promotional fare of Rp8 was applied. The Jakarta Transportation Agency data
showed more than 210,000 passengers used the line in September 2026, representing a 58% rise over August. Trains currently run every 15 minutes from 05:30 to 20:00 along the entire route, with partial service limited to the original Kelapa Gading to Velodrome section continuing until 23:00. The full end-to-end travel time on the extended line is approximately 28 minutes.
The Rp4.1 trillion (US$227 million) construction for Phase 1B was undertaken by KSO Waskita Nindya LRS, a joint operation including state contractor Waskita Karya, building the extension on behalf of PT Jakarta Propertindo, which is owned by the Jakarta government. Governor
Pramono Anung confirmed that the total investment across the 12.2 km line has reached Rp12.1 trillion (US$670 million), fully funded by the provincial government.
The trains operating on the line comprise eight two-car trainsets originally supplied for the initial section. Hyundai Rotem secured a US$33 million contract in 2017 to deliver 16 cars, managing design and bogie supply, while South Korean manufacturer Woojin Industrial Systems handled the bodyshell manufacture and final assembly. Each articulated trainset has a maximum capacity of 270 passengers and can reach speeds up to 90 km/h.
Future Extensions and Financing
Plans are underway for further expansions, including Phase 1C, a
2 km extension from Manggarai to Dukuh Atas in Central Jakarta. This extension will facilitate connections with MRT Jakarta, commuter rail lines, and TransJakarta buses. Construction is expected to start by January 2027 and reach completion by August 2028. The estimated cost of Phase 1C has risen from Rp2.1 trillion to Rp2.7 trillion (US$150 million), mainly due to the need to add about 16 more trainsets.
Another planned project, Phase 2A, aims to extend the line 8.2 km from Kelapa Gading to the Jakarta International Stadium, adding six stations with a projected budget of Rp7.8 trillion (US$432 million). This project
is listed as an investment opportunity and is expected to commence in 2027 through public-private partnership or alternative financing mechanisms.
The Jakarta government has sought financial support from Danantara, Indonesia’s sovereign wealth fund, for these expansion projects. President Prabowo agreed with this approach, emphasizing the national importance of Jakarta’s transit development.
Official Statements
Aditia Kesuma Negara, President Director of PT LRT Jakarta, described the inauguration as the start of heightened operational responsibility, pledging to prioritise safety and reliability to maintain public trust. Governor Pramono Anung disclosed the ongoing investment scale and confirmed the schedule and increased cost estimates for Phase 1C.
President
Prabowo highlighted the critical role of Danantara in supporting the LRT expansions, noting that Jakarta belongs to the entire nation, not just its residents.